In Lake County, Illinois, TMC physical components cost $1.8 million.
TMC Physical Component Cost in Lake County, IL
Illinois, United States
In Lake County, Illinois, a traffic management center (TMC) was constructed to serve at a central hub for all communications related to real-time traffic and maintenance activities used to support advanced traffic management and signal system operations. The data below extracted from Table 9-1 of the source report highlights capital cost items in the preliminary budget.
|
Budget Item
|
Capital Cost
|
|---|---|
| TMC PS&E (Plans, Specs. & Engineering) / Construction support (10%) |
$125,509
|
| TMC Construction |
$1,255,089
|
| Generator and Uninterrupted Power Supply |
$150,000
|
| Video Wall |
$175,000
|
| TMC Phones |
$4,650
|
| TMC console |
$59,000
|
| Office Furniture |
$22,400
|
| Sub-Total TMC |
$1,805,048
|
| Construction of Fiber Optic Infrastructure and Comm. Backbone Equip. (per corridor) |
$1,000,000
|
| 3 Dynamic message signs |
$120,000
|
| 3 Highway advisory radios |
$120,000
|
| 5 CCTV cameras |
$100,000
|
| 20 Highway advisory radio signs |
$10,000
|
| Field Elements and Comm. PS&E (10%) |
$267,000
|
| Integration oversight and Mgmt. |
$222,000
|
| System integration & ATMS Functions |
$850,000
|
| Hardware and COTS Software |
$210,000
|
| Signal System - Central (including integration) |
$475,000
|
| Signal System - Firmware upgrades |
$320,000
|
| Signal Timing |
$50,000
|
| Sub-Total Excluding TMC |
$3,744,000
|
| Contingency |
$227,210
|
| TOTAL |
$5,776,258
|
In addition to the capital costs listed above, the annual O&M costs required to maintain communications between the TMC and field devices using a fiber optic network were estimated at $2,400 per pan-tilt-zoom camera, $1,200 per master controller, and $600 per vehicle detection station camera.
Staffing requirements for the facility were estimated at $120,000 to $130,000 per year for two TMC Operators (initially 2 full time equivalents) as well as system support and administration. Training during the first year of operations was estimated at $20,000.
Lake County TMC Study: Implementation Phasing Plan - Version 2.0
TMC physical components: $1.8 million (2003)