Thoughtful Planning and Implementation of Mobility on Demand (MOD), Including Understanding its Impacts on the Transportation Network, are Critical to Balancing Public Goals with Commercial Interests.

Some of the most important findings from this project include: Consumers are increasingly assigning economic values to modes and engaging in multimodal decision-making processes based on a variety…
Content type
Date Posted
11/30/2020

Emphasize financial sustainability in concept development. Keep long-term funding goals in mind when tailoring a concept to meet a short-term budget.

LESSONS LEARNED FROM USDOT PERSPECTIVE:     Program Management (Acquisition Strategy and Outreach) Conduct consistent and organized meetings with the entire acquisition team (federal…
Content type
Date Posted
03/27/2017

To avoid surprises after implementation of a comprehensive transit ITS program, perform a detailed analysis of costs for operations and maintenance during the project planning phase.

A comprehensive transit ITS deployment must include a detailed analysis of operations and maintenance costs. Lessons learned from the Regional Transportation Commission (RTC) of Washoe County’s…
Content type
Date Posted
01/18/2012

Examine multiple funding sources and anticipate unforeseen costs associated with deploying transit ITS.

As always, there are issues with funding any transportation project, and ITS in particular, that require recommendations and advice. The transit agencies in this case study brought forward a number…
Content type
Date Posted
02/15/2007

Beware that inter-agency funding arrangements can lead to delays in awarding and executing project contracts.

The funding mechanism and its execution have enormous influence on the success of ITS projects. In the case of ITS Earmark projects, since a portion of the funding is designated by Congressional…
Content type
Date Posted
11/22/2006