A Ramp Metering System at Four Entrance Ramps on I-540 Was Projected to Cost $1,655,560 over A Ten-year Period (2017 to 2027).

A State Evaluation Report Assessed Ramp Metering for Interstate Highways in North Carolina.

Made Public Date
03/29/2022
Identifier
2022-SC00507
TwitterLinkedInFacebook

Ramp metering, deployed by installing traffic signals on the on-ramp of a freeway, is a freeway active traffic management (ATM) strategy that is often used to control the frequency of traffic onto the mainline, allowing efficient use of existing freeway capacity. This study examined the post-installation impacts of four on‐ramp signals on the westbound lanes of I‐540 in Wake County, North Carolina, using before‐and‐after traffic data. Analyses were conducted using available data from September 2017 (pre‐on‐ramp signals) and October 1, 2017 – September 30, 2018 (post‐on‐ramp signals). All changes to on‐ramp signal operations, outages, and other variables which may influence regular traffic operations in the first two to three months of operation were documented. A benefit and cost analysis were conducted to forecast the net savings over 10 years. This study also provided tools for North Carolina Department of Transportation (NCDOT) to calibrate North Carolina’s on‐ramp signal evaluation framework and planning models to forecast and evaluate on‐ramp signal outcomes into the future.

Capital and programing costs were based on engineering firm estimates. Future projections were discounted with a three percent discount rate. Maintenance costs included the annual and incremental operations and upkeep costs needed to keep a facility operational and the cost of revising an intersection at the end of its anticipated service life. It is not expected that the facility will need to be replaced until after 10 years. Year 2017 is used as the baseline year. The capital cost, programing and operational investments for the ramp metering systems with signals installed on four ramps are shown below.

Table 1: Total Capital, Programming, and Operational Investments

Cost

Installation Year 2017

Total Projected for Years 2018 – 2027*

Installation (four On-Ramp Signals)

$830,170

N/A

One-time Programming

$405,00

N/A

Operations and Maintenance

N/A

$63,900

NCDOT Staff Support

N/A

$356,490

Facility Replacement

N/A

$0

Total Cost for 2017-2027

 

$1,655,560

*Projections are discounted into the future

 

The capital cost breakdown for individual ramp metering site is shown below:

 

Table 2: Individual On‐Ramp Signal Capital Costs

Location

Ramp Metering Configuration

Roadway Improvement

Capital Cost

Site 1

Two-lane

Extended two-lane ramp 130 ft with 720 ft merge taper

$238,240

Site 2

Two-lane

Extended two-lane ramp 130 ft with 720 ft merge taper

$214,364

Site 3

Two-lane

None

$135,632

Site 4

Two-lane

Extended two-lane ramp 130 ft with 720 ft merge taper

$241,934

 

The long‐term costs associated with the staff required to support the operations of the I‐540 WB on‐ramp signals are shown below.

 

Table 3: Staffing Costs for On-Ramp Signal Operations

Staff Support Cost

 

Weekly Compensation

Annual Compensation

Total Projected for Years 2018 – 27*

Traffic Management Center (TMC) Floor Operator

$636

$32,197

$274,645

TMC Engineer

$190

$9,595

$81,845

Total

$826

$41,792

$356,490

*Projections are discounted into the future

 

Planning Level Evaluation of the Effects of Ramp Metering on North Carolina Freeways Final Report

Planning Level Evaluation of the Effects of Ramp Metering on North Carolina Freeways Final Report
Source Publication Date
02/01/2019
Author
Davis, Joy; Thomas Chase; Behzad Aghdashi; Chris Cunningham; Weston Head; James Poslusny; and Terry Karlson
Publisher
Prepared by North Carolina State University for the North Carolina DOT
Other Reference Number
Report No. 2018‐19
System Cost

See summary

System Cost Subsystem