A well designed signal retiming plan covering 8.7 miles resulted in 16,322 hours of travel time savings and 982 tons of CO2 reductions.

FINDINGSTravel Time savings on US-31 in Kokomo, Indiana RoadwayPlanMedian Travel Time Savings (min)Percentage of Daily TrafficTravel Time Savings (hours)Travel Time Savings ($)CO2 Reduction (tons)CO2…
Content type
Date Posted
08/29/2014

One-time capital costs for controller-based high resolution data collection systems were estimated at $3,120 per intersection.

In Indiana, a corridor with approximately 100 intersections was upgraded to improve signal timing optimization, enable capacity analysis, and support future adaptive signal control operations.…
Content type
Made Public Date
08/29/2014