Author
Tina Wu, Matt Weatherford, Ancila Kaiparambil, Linna Zhang
Benefit Summary HTML

Beginning in 2000, the Regional Transportation Commission (RTC) of Washoe County, Nevada, began planning for ITS implementation into their regional transit services. They set goals that aligned with the U.S. DOT's six goal areas for ITS projects and applied for funding for their project through the FTA. By 2007, RTC had completed the installation, testing and acceptance of the ITS components. This report is an evaluation of RTC transit ITS. It covers both planned and deployed components of their system, evaluating how well the system works to meet their initial goals and describing the functionality of the various components of the system. The report also includes lessons learned by RTC as they progressed through the procurement, deployment and operation processes in order to be a resource for other agencies contemplating similar ITS investments. RTC deployed automatic vehicle location (AVL), remote engine diagnostics (RED), computer-aided dispatch software (CAD), and automatic passenger counters (APC) in their vehicles. They also installed, but have not activated traffic signal priority (TSP) components.

Hyperlink Exit Door
No
Last Modified Date
Lesson Background HTML

In 1999, the Regional Transportation Commission (RTC) of Washoe County, Nevada entered into a cooperative agreement with the Federal Transit Administration (FTA) to procure and implement Intelligent Transportation Systems (ITS) for its fixed-route and paratransit services. RTC's transit ITS deployment initiative was a multi-year funding project and the total cost agreed to was $4,750,000, with a funding split of 80 percent federal and 20 local. RTC began the procurement process in 2000, the implementation in 2002, and completed implementation and acceptance testing in 2007. RTC staff and its passengers have become accustomed to the system and its functionality. Key ITS technologies deployed were:

  • Automatic Vehicle Location (AVL) on fixed-route, paratransit and supervisor vehicles
  • Computer-Aided Dispatch
  • Paratransit Scheduling and Reservation Software
  • Fixed-Route Scheduling Software
  • DataMart™
  • Automated Passenger Counters
  • Real-Time Traveler Information for Fixed-Route Vehicles
  • Remote Engine Diagnostics
  • Automated Stop Announcements
  • Transit Signal Priority
  • Mobile Supervisor

An evaluation report, entitled "Regional Transportation Commission of Washoe County Transit Intelligent Transportation System Implementation Evaluation" was published in March 2010. The project evaluators compared baseline pre-transit ITS data and post-transit ITS data, measured the quantitative and qualitative impacts on operational efficiency, observed how RTC staff performed their responsibilities, and identified a set of lessons learned.

Pages
118
POC
Jim Bunch Noblis, Charlene Wilder FTA
Publication Sort Date
Publisher
Federal Transit Administration U.S. Department of Transportation
Reviewer
Source ID
1136
Title
Regional Transportation Commission of Washoe County Intelligent Transportation System Implementation Evaluation Study
UNID
2BEADA2DD7F41203852578AB006B49E5
Source Review
External URL Disclaimer

(Our website has many links to other organizations. While we offer these electronic linkages for your convenience in accessing transportation-related information, please be aware that when you exit our website, the privacy and accessibility policies stated on our website may not be the same as that on other websites.)