UC2012-01916

Cost Subsystem
Description

Cost estimate to convert a freeway shoulder lane into a MnPASS Lane on Corridor 3B. I-35E: TH 36 to CR E.

Capital Cost Per Unit
$9,250,000.00
OM Cost Per Unit
$50,000.00
Adjusted Capital Cost Per Unit
$13,100,000.00
Adjusted O&M Cost Per Unit
$70,600.00
Reported Units
3.8 miles
Lifetime
20
Unit Cost Type
Unit
Per Mile
CPI ID
6
CPI Name

CIU1010000000710I

Year
2010
Notes
Total capital cost: $8 million to $10.5 million per mile (includes ATM and non-ITS infrastructure). ATM component: $6 million per corridor (includes tolling equipment, signs, sign structures, and communications infrastructure).