Note: The date in parentheses under the capital cost value and O&M cost value represents the dollar year of the cost values. All costs are in $K.
Unit Cost Element | IDAS# | Life (years) | Capital Cost $K (Year) | O&M Cost $K/year (Year) | Description | |
---|---|---|---|---|---|---|
Electronic Toll Collection Structure | TP004 | 20 | 10.00 - 7112.50 (2013) | Mainline structure. |
||
Electronic Toll Reader | TP001 | 10 | 2.00 - 5.00 (2001) | 0.20 - 0.50 (2001) | Readers (per lane). O&M is estimated at 10% of capital cost. |
|
Electronic Toll Collection Software | TP003 | 10 | 5.00 - 10.00 (1995) | Includes COTS software and database. |
||
High-Speed Camera | TP002 | 10 | 7.00 - 10.00 (2003) | 0.50 - 1.00 (1995) | Cost includes one camera per two lanes. |
|
Other Unit Cost Elements | - | Summary values under development |