Note: Equipment list adjusted to 2014 dollars. The date in parentheses under the capital cost value and O&M cost value represents the dollar year from which the cost value was adjusted. All costs are in $K.
Unit Cost Element | IDAS# | Life (years) | Capital Cost $K, 2014 Dollars (Year) | O&M Cost $K/year, Dollars (Year) | Description |
---|---|---|---|---|---|
Electronic Toll Collection Structure | TP004 | 20 | 14.00 - 22.00 (1995) | Mainline structure. |
|
Electronic Toll Reader | TP001 | 10 | 1.00 - 4.00 (2001) | 0.10 - 0.40 (2001) | Readers (per lane). O&M is estimated at 10% of capital cost. |
Electronic Toll Collection Software | TP003 | 10 | 5.00 - 10.00 (1995) | Includes COTS software and database. |
|
High-Speed Camera | TP002 | 10 | 5.00 - 8.00 (2003) | 0.30 - 0.60 (1995) | Cost includes one camera per two lanes. |