Description
Cost based on physical building cost/ comm infrastructure. This is based on the 12,000 sq.ft. building for Artemis Control Center in Cincinnati. Includes all costs from ground-breaking to ribbon-cutting. Miami also has a 12,000 sq.ft. building that was remodeled for Florida DOT.
Lifetime
20
Made Public Date
Match to Unit Cost Element
false
Part Of Unit Cost Element Architecture
false
Taxonomy
UNID
A5D31B3938C7C43F85257723006E0D41
Unit
Lump Sum (LS)
Cost Type
Capital Cost Per Unit
12000000.00
OM Cost Per Unit
60000.00
Geo