The cost to equip 20 intersections with DSRC was estimated at $309,000 in Gwinnett County, Georgia.

Gwinnett County's Connected Vehicle Technology Master Plan details cost data to implement DSRC.

Made Public Date
10/26/2020
Identifier
2020-SC00468
TwitterLinkedInFacebook

As part of a Smart Corridor project, Gwinnett County will deploy roadside units (RSUs), onboard units (OBUs), and test software, in collaboration with GDOT to support implementation of a Connected Vehicle Technology Master Plan (CVTMP).  The overall goal is to deploy dedicated short range communication (DSRC) equipment at 92 state route intersections including 36  intersections on corridors of SR 140 and SR 141.

Applications including Signal Phase and Timing Information (SPaT), Emergency Vehicle Preemption (EVP), Transit Signal Priority (TSP), Construction and Maintenance Vehicle Alerts, Railroad Intersection Blocked Alerts, and Pedestrian Presence Alerts (PPA) were scheduled to be implemented and tested in 2020.

The table below excerpted from the source report provides high-level cost estimates for several system elements required for the deployment. The estimates were based on cost data collected from existing deployments. Additional functionality being integrated into these systems such as over-the-air updates, are expected to decrease deployment costs for similar system in the future.

The RSU cost estimate included the cost for mapping the intersection in addition to purchasing RSUs and installing them in the field.

Connected Vehicle Hardware Costs (includes purchase and installation)

Device

Device with Installation Cost Estimate

DSRC RSU System

$4,000 - $6,000 per intersection

Edge Device

$250 - $450 per intersection

DSRC OBU System

$1,000 - $5000 per unit

HMI

$1,000 - $3,000 per unit

C-V2X Device

$6,000 - $7,000 per intersection

The tables below excerpted from the source report provide an overview of a sample project with rough estimates for a system with 20 intersections outfitted with connected vehicle technology.

 Sample Project Field Installations

Field Installation

# of Units + Install + Programming

Unit Cost

Total Cost

Roadside Unit

20

$5,000

$100,000

MAP Message Development

20

$1,500

$30,000

Edge processing

20

$350

$7,000

Software (units=intersections)

20

$7,000

$140,000

Service (units=years)

3

$10,000

$30,000

Cybersecurity (SCMS)

20

$100

$2,000

TOTAL

 

 

$309,000

Sample Project Vehicle Installations

Field Installation

# of Units + Install + Programming

Unit Cost

Total Cost

OBU

20

$3,000

$100,000

HMI

20

$5,000

$60,000

Cybersecurity (SCMS)

20

$100

$2,000

TOTAL

 

 

$162,000

 

System Cost

DSRC at 20 intersections: $309K