A fiber optic communications network supporting traffic operations on a 17 mile section of US-24 in Colorado was estimated to cost $2.5 million.

CDOT’s Smart Mobility Plan fiber optics project.

Made Public Date
03/13/2019

110

Colorado Springs
Colorado
United States
Identifier
2019-00419
TwitterLinkedInFacebook

Summary Information

As part of the Colorado Department of Transportation (CDOT) Smart Mobility Plan, CDOT started construction on a fiber optic backhaul in Colorado Springs to improve real-time access to traffic-monitoring cameras, traffic detectors, variable message signs, road weather information system stations, and traffic signal controllers to improve emergency response actions, traveler information, and corridor traffic flow.

Initiated in January 2019, the project is anticipated to include 17 miles of fiber optic cable along US-24 between Woodland Park and I-25/Cimarron Street at a cost of approximately $2.5 million. Project duration was estimated at nine months.

US 24 ITS Fiber Optic Installation

US 24 ITS Fiber Optic Installation
Publication Sort Date
01/01/2019
Publisher
Colorado DOT

(Our website has many links to other organizations. While we offer these electronic linkages for your convenience in accessing transportation-related information, please be aware that when you exit our website, the privacy and accessibility policies stated on our website may not be the same as that on other websites.)

System Cost

See Summary.