Installing a Comprehensive Structural Health Monitoring System on a Critical Cable-Stay Bridge in West Virginia Cost $812,000.

WVDOT’s SMART Grant Project Estimated Costs Based on a Proof-of-Concept Deployment of Structural Health Monitoring System on an Ohio River Bridge.

Made Public Date
10/26/2026
Identifier
2026-sc00606

Aging and structurally deficient bridges continue to increase the need for effective, efficient, and scalable inspection and maintenance strategies. To address this challenge, this SMART grant project evaluated whether continuous structural health monitoring (SHM) data could identify bridge deterioration, support incident response, and improve long-term asset management. The West Virginia Department of Transportation (WVDOT) Division of Highways (DOH) installed a wireless structural health monitoring (SHM) system with 57 sensors on the East Huntington/Gunner Gatski Bridge from November 18 to 22, 2024. The study evaluated system data collected between the November 2024 installation and March 1, 2025, the end of the performance period. The cable-stay bridge carried more than 14,000 vehicles per day between Huntington, West Virginia, and Proctorville, Ohio. The system included 39 accelerometers (20 on the cables and 19 on the deck and towers), six tiltmeters, four crackmeters, six displacement sensors, a weather station, and a vessel-impact detection system. The study proposed extending monitoring to six additional Ohio River bridges.

The project was completed within its $812,000 budget, which covered DOH labor and grant administration, travel, SHM equipment and supplies, consultant support for system planning, installation and monitoring, maintenance of traffic for installation access, and grant reporting.

Table 1. SHM System Deployment Costs 

Cost Items

Cost

Share

Direct labor

$80,000 

9.90%

Travel

$4,000 

0.50%

Equipment

$110,000 

13.50%

Supplies

$208,000 

25.60%

Contractual services

$400,000 

49.30%

Reporting

$10,000 

1.20%

Fringe benefits

$0 

0.00%

Construction

Not reported

-

Total

$812,000

100.00%

For the next phase, the study provided a preliminary $12 million estimate for deploying SHM systems on six additional Ohio River bridges over a performance period of up to 36 months. The estimate included initial deployment costs and operational costs for maintaining the systems and evaluating the data collected during the performance period, as shown in Table 2.

Table 2. Projected Costs for Six Additional Bridges

Estimated Cost Items

Cost

Share

Direct labor

$4,110,185 

34.25%

Travel

$8,000 

0.07%

Equipment

$628,271 

5.24%

Supplies

$1,960,494 

16.34%

Contractual

$5,283,050

44.03%

Other

$10,000 

0.08%

Construction

Not reported

-

Total

$12,000,000

100.00%

System Cost

The SHM proof-of-concept deployment on one bridge cost $812,000, while the proposed deployment on six additional bridges was estimated at $12 million.

System Cost Subsystem