A Smart Work Zone System Contracted for a 2.5-year Project on I-44 in Missouri Cost $300,000 or Approximately $2,692 per Week.

Missouri Department of Transportation Evaluation Reported Smart Work Zone Contract Costs from a 2025 Road Widening Project Near Springfield.  

Made Public Date
10/26/2026
Identifier
2026-sc00605

Effective work zone traffic management reduces delays, protects travelers and workers, supports timely construction, and maintains access for travelers. To advance its Transportation Systems Management and Operations (TSMO) and work zone management priorities, the Missouri Department of Transportation (MoDOT) has been identifying practical strategies that address workforce needs and improve safety. The objective of this study was to evaluate the effectiveness of Smart Work Zone (SWZ) strategies, with the goal of improving work zone safety and operations and applying best practices to construction projects statewide. The evaluation focused on a road-widening and bridge/ramp construction project on Interstate 44 (I-44) in Greene County, from Kansas Expressway/Missouri Route 13 to US Route 65 in Springfield. A queue detection system (with radar sensors and portable changeable message signs), and temporary long-term rumble strips were deployed along an approximately 4.5-mile segment of I-44 in April 2025. The field evaluation took place from May to November 2025.

The SWZ components of the I-44 Springfield project were contracted to be provided over an estimated 780 days of the 2.5-year project duration, with separate contracts for the East and West portion of the overall project. A total of eight radar sensors and nine portable changeable message signs were specified in the construction plan. The SWZ costs accounted for 3.65 percent of all temporary traffic control costs for the East project and 3.02 percent for the West project.

Cost Description

Cost (2025 USD)

Temporary traffic control, East project

$4,111,246

SWZ, East project

$150,000

Temporary traffic control, West project

$4,962,895

SWZ, West project

$150,000

Addition of Radar Speed Advisory System (speed feedback signs)

$27,000

Overall I-44 road project cost

$70,750,000

System Cost

Smart Work Zone system cost $300,000 for a 2.5-year project on a 4.7-mile freeway segment, or approximately $2,392 per week.