Arizona DOT review of statewide rural ITS through June 2007.
Statewide, Arizona, United States
This project investigated rural ITS for the Arizona Department of Transportation (ADOT) and reviewed current practices and concepts used by transportation agencies across the country. The primary focus was on ITS maintenance, weather information systems (RWIS), highway advisory radio (HAR), motorist assistance patrols (MAPs), and information sharing/training applications. Initial tasks included interviews with ADOT engineers, maintenance staff, and managers regarding rural ITS infrastructure elements implemented or decommissioned statewide through June 2007.
Estimates of initial capital costs, annual operations and maintenance costs, and resulting five-year funding estimates were provided for the following ITS deployment concepts.
Focus Area | Deployment Concept | Initial Capital Costs | Operating & Maintenance Costs | Engineers Opinion of Cost (Over 5 Years) |
---|---|---|---|---|
ITS Maintenance | Third-Party ITS Operations & Maintenance Contracting - $200,000 Annual Contract |
-
|
$200,000
|
$1,000,000
|
Truck Escape Ramp Monitoring - 7 Sites at $125,000 Per Site (Total) |
$700,000
|
$35,000
|
$875,000
|
|
Expansion of Rural Cellular Coverage - Major US Highways & State Routes |
$74,999
|
-
|
$74,999
|
|
DMS Construction - 8 Sites at $312,500 Per Site (Total) |
$2,300,000
|
$40,000
|
$2,500,000
|
|
Weather Information Systems | Participation in Clarus - Database Development & Maintenance, Coordination with National Agency |
-
|
$100,000
|
$500,000
|
RWIS Deployment - 48 Sites at $112,000 Per Site (Total) |
$768,000
|
$921,600
|
$5,376,000
|
|
State Meteorologist- 1 Position at $85,000 Annual Salary |
-
|
$85,000
|
$425,000
|
|
Low Cost Weather Stations - 40 Sites at $2,500 Per Site (Total) |
$64,000
|
$7,200
|
$100,000
|
|
Low Visibility Detection - 15 Sites at $75,000 Per Site (Total) |
$900,000
|
$45,000
|
$1,125,000
|
|
Bridge Deck Anti-Icing Monitoring - 3 Locations at $100,000 / Site (Total) |
$240,000
|
$12,000
|
$300,000
|
|
Develop IGAs for Flood Detection Data - 11 Counties at $70,000 (each) |
$770,000
|
-
|
$770,000
|
|
Mobile Data Collection for Snowplows - 54 Snowplows at $12,000 / Vehicle (Total), w/ satellite communication |
$540,000
|
$21,600
|
$648,000
|
|
Traveler Information Systems | Portable HAR - 8 Units at $30,000 Each (Total) |
$200,000
|
$8,000
|
$240,000
|
Work Zone HAR Specification Development - One-Time Consultant Fee |
$5,000
|
-
|
$5,000
|
|
Permanent HAR Sites - 20 Sites at $25,000 Per Site (Total) |
$400,000
|
$20,000
|
$500,000
|
|
Intelligent Rest Area Deployment - 15 Sites at $48,000 Per Site (Total) |
$645,000
|
$15,000
|
$720,000
|
|
Corridor Travel Time Monitoring - 8 Sites at $112,500 Per Site (Total) |
$800,000
|
$20,000
|
$900,000
|
|
Emergency Detour Routing - 33 EMS at $6,000 Per Sign (Total) |
$148,500
|
$9,900
|
$198,000
|
|
Motorist Assistance and Safety Services | MAP Specification Development - One-Time Consultant Fee |
$30,000
|
-
|
$30,000
|
CRASH Vehicles - 20 Vehicles at $90,000 Per Vehicle |
-
|
$360,000
|
$1,800,000
|
|
Enhance Field Communications with Phoenix District via 800 MHz Radios - 50 Units at $1,500 Per Unit Installed |
$75,000
|
-
|
$75,000
|
|
ADOT VHF Radios in DPS Vehicles - 440 Units at $1,500 Per Installation - Total $660,000: *All Costs by DPS |
-
|
-
|
-
|
|
District Training Programs - Consultant Fees for Protocol Updates |
-
|
$8,000
|
$40,000
|
|
Information Sharing/Training | Oversized Load Management - Initial Implementation of System. * System Expansion and On-Going Costs Absorbed by Industry Agencies |
$400,000
|
-
|
$400,000
|
Simulator Interagency Training - LTAP - Supplemental Activities to Establish Coordination with Partner Agencies |
-
|
$12,000
|
$60,000
|
|
Internal Information Sharing - 5 Conferences Per Year for 20 Participants |
-
|
$50,000
|
$250,000
|
Conceptual cost estimates for each ITS focus area are shown in the table below drawn from the sources report:
Focus Areas Deployment Concepts | Opinion of Cost |
---|---|
ITS Maintenance |
$4,450,000
|
Weather Information Systems |
$9,244,000
|
Traveler Information Systems |
$2,563,000
|
Motorist Assistance and Safety Services |
$1,945,000
|
Information Sharing |
$710,000
|
TOTAL OVER 5 YEARS |
$18,912,000
|
AVERAGE TOTAL COST PER YEAR |
$3,782,400
|
ITS Concepts For Rural Corridor Management: Final Report 615